Ferdinand bridge
For the development of the Ötztal Cycle Path a bike bridge over the Ötztaler Ache was built in Längenfeld.
Span: 65.7 m
Execution class EXC3 acc. EN 1090-2
Due to the cramped space situation on site, the bridge was completely pre-assembled on an assembly site.
Using special module transporters, the 72-tons bridge was transported to the lifting point and lifted into the final position with two mobile cranes.
Rubrik:
bridge building
Leistungsumfang:
Delivery and installation of the steel construction including corrosion protection and bridge equipment.
Kunde:
Porr Bau GmbH
Bauherr:
Ötztal tourism
Ausführungszeit:
summer 2018